SEARCH SITE GO >
ABOUT ELI
YOUR COMMUNITY
Ward 5 Calendar
Helpful LINKs
Goings-On in The Valley
Community Associations, Facilities and Partners
Roadwork Report
Latest Police Report
Legion Newsletter/Events
Rural Connections Newsletter
Ward 5 Health Program Spring 2010
Police Board Newsletter
Planned Roadwork 2010
Ottawa Public Health Board Anual Report
Police Service Annual Report 2009
Annual Crime Statistics 2009
Well Water Testing
NEWS & ANNOUNCEMENTS
WHERE I STAND
OTTAWA.CA
CONTACT
WHAT OTHERS SAY
EVENTS & IMAGES
Frequently Asked Questions


Ward 5 Web Calendar HERE

City Hall News Releases HERE

Brief News and Announcements
updated  4 September
[
Search archives HERE  under "Announcements" ]
 
[04 Sep] Well Water Testing Blitz
3-12 October ...MORE
[26 Aug] Labour Day Schedule Changes
Monday, September 6. ...MORE
[17 Aug] WM's Response to Council's Comments on WCEC TofR
Company's response to City's comments on the Terms of Reference for the EA on the West Carleton Environmental Centre ...MORE
[14 Aug] Capital Cleanup Weekend
Register your group now for September 24 - 26 weekend. ...MORE
[27 Jul] "Are You Ready" - Rural Training
Register for September sessions ...MORE
Archives
 
MEMBER LOGIN GO >
Working on Our Rural Roads

Ward 5 Construction Projects Map

Infrastructure Stimulus Fund construction projects underway in the City of Ottawa include sewage, culvert and drainage improvements; watermains; road resurfacing, widening and new construction; sidewalk renewal and new construction; streetscaping projects; traffic management improvements; multi-use pathway construction; Transitway improvements; recreational and cultural facilities; parks; and libraries. See HERE for a map of the Ward 5 projects [ 700 KB PDF file]

Our rural roads are our 'transit system.' The maintenance of Ottawa's rural roads is important to the livelihood and daily life of our Ward. This was acknowledged by the Rural Summits and we assigned a high priority to this area of work

Some background is found HERE on the criteria that are used to help determine the essential roadwork projects.

To confirm whether a road is going to be closed for maintenance work, use this SEARCH tool

The 2009 Construction Season has just started.  See the LIST for the Ward 5 roadwork planned for 2009 Construction Season. In addition, we are hopeful of receiving additional  funding from the Fedral Goverment's Infrastructure Stimulus program. Potential additional projects under that program are found HERE.

Below are listings of the Ward 5 roadwork that is imminent, in progress, or completed. Listings are  in alphabetical order by road.

Questions can be referred to Kerry Bourgaize.


WEEKLY PROGRESS REPORT - WEEK OF 24 August 2010

Road

From

To

Description

Start Date Week Of

Completion Date

Comments

Impact on Traffic

Burnt Lands Rd

1.9km N of March Rd

2.7km N of March Rd

Guiderail Upgrades

Aug 24-10

Oct 29-10

Not Started

Low

Canon Smith Dr

Fitzroy St

80m N of Aylwin Rd

Asphaltic Overlay

June 15-10

Aug 31-10

Ongoing

Medium

Huntmar Dr

Old Carp Rd

March Rd

Asphaltic Overlay

June 20-10

Aug 31-10

Ongoing

Medium

March Valley Rd

Klondike Rd

Riddell Dr

Surface Treatment

June 14-10

Aug 31-10

Ongoing

Low

Northwoods Dr

175m N of Buckhams Bay Rd

Dead End

Surface Treatment

June 14-10

Aug 31-10

Ongoing

Low

Thomas Dolan Pkwy

700m E of Carp Rd

 

Guiderail Upgrades

Aug 30-10

Oct 29-10

Not Started

Low

Tranquility Ln

Dead End

Buckhams Bay Rd

Surface Treatment

June 14-10

Aug 31-10

Ongoing

Low

Willola Beach Rd

Moorhead Dr

Canon Smith Dr

Asphaltic Overlay

June 14-10

Aug 31-10

Ongoing

Low

 

WORK RECENTLY COMPLETED IN WARD 5

Road

From

To

Description

Start Date Week Of

Completion Date

Armitage Rd

Greenland Rd

440m N of Gill Park Ln

Surface Treatment

June 28-10

Aug 13-10

Burnt Lands Rd

March Rd

1.5 km N of March Rd

Surface Treatment

May 26-10

June 30-10

Burnt Lands Rd

1.5 km N of March Rd

Vaughan Side Rd

Surface Treatment

May 26-10

June 30-10

Canon Smith Dr

550m N of Willola Beach Rd

1,100m N of Willola Beach Rd

Surface Treatment

July 5-10

Aug 13-10

Canon Smith Dr

Galetta Side Rd

Fitzroy St

Surface Treatment

July 5-10

Aug 13-10

Canon Smith Dr

80m N of Aylwin Rd

Willola Beach Rd

Surface Treatment

July 5-10

Aug 13-10

Greenbank Rd

Iris St.

S Limit of Hwy 417

Asphaltic Overlay

June 21-10

Aug 13-10

Highview Rd

Buckhams Bay Rd

Dead End

Surface Treatment

June 29-10

Aug 13-10

March Valley Rd

Klondike Rd

Riddell Dr

Surface Treatment

May 20-10

June 30-10

McGee Side Rd

John Cavanaugh Rd

200m E of Oak Creek Rd

Surface Treatment

May 26-10

Aug 13-10

Merivale Rd @ Meadowlands Dr N/B

171m South of Stopbar

Stopbar

Pavement Preservation Micro Surfacing

July 21-10

Aug 31-10

Moonstone Rd

Rothbourne Rd

Dead End

Surface Treatment

May 25-10

Aug 13-10

Northwoods Dr

175m N of Buckhams Bay Rd

Dead End

Surface Treatment

June 2-10

June 30-10

Oak Creek Rd

Richardson Side Rd

McGee Side Rd

Surface Treatment

May 26-10

Aug 13-10

Old Almonte Rd

1 Km W of Corkery Rd

Corkery Rd

Surface Treatment

May 25-10

June 30-10

Old Almonte Rd

Spruce Ridge Rd

Northshire Dr

Surface Treatment

May 27-10

Aug 13-10

Old Almonte Rd

Northshire Dr

David Manchester Rd

Surface Treatment

May 27-10

Aug 13-10

Old Almonte Rd

Upper Dwyer Hill Rd

800m E of Upper Dwyer Hill Rd

Surface Treatment

May 27-10

Aug 31-10

Tranquility Ln

Dead End

Buckhams Bay Rd

Surface Treatment

June 2-10

June 30-10

Vaughan Side Rd

Burnt Lands Rd

Upper Dwyer Hill Rd

Surface Treatment

May 26-10

June 30-10






 

 